The shed is 20'x8' and the lean-too is 20'x8. We will have a 110' foot underground run to the house, and a 150' foot underground run to the outbuilding. We are completing only the house run this fall, but we will rough in and plan for the outbuilding to be completed for the heating season of 2010.
The shed portion of the outbuilding has a poured concrete pad that is reinforced with rebar, and a little thicker than required, but a little over design is not a bad idea.
We will insulate below grade with "blue board" to prevent the pad from moving with the freeze and thaw cylcles. The lean-too area will get graded, and filled with modified 2A stone compacted, then 2 stone for drainage.
The day we poured was a beautiful fall day in eastern PA. The leaves were in full color, and it was great to be outside working. Everything went smoothly, we were done, and covering the job with plastic to cure for a week by noon. After the pad is cured we will place the Garn, and build the shed around the boiler.
First off, I want to thank you for taking the time to post pictures of the installation process of your Garn 2000.
ReplyDeleteIf you had to do it again, would you make the shed the same dimensions? Would you go wider than 8 feet; would you go shorter than 20 feet? What did you do to have an easy access to the back of the boiler should there be any problems with it?